How do I answer this question? Can you provide the steps also.

Product backlog has got 400 story points worth work.
Baseline velocity is 25 story points.
Total budget to complete this whole work is 200,000.
At the end of second iteration, actual cost = 22,500 and story points completed = 60.
What is the SPI value?
Mark one answer:

A. 1.2
B. 1.1
C. 1
D. 0.83

Created 10 months ago by kenny_faulks@yahoo.com

kenny_faulks@yahoo.com

400 Story Points Total/25 story points velocity = 16 Iterations After 2nd Iteration: 60 Story Points Completed/400 Story Points Total = 15% Finished EV = Actual % Completed * BAC 15% Finished/$200,000 BAC (Budget at Completion) = $30,000 Planned % Complete 2 Iterations Complete/16 Iterations = 12.5% Planned PV = Planned % Complete * BAC 12.5% * $200,000 = $25,000 SPI = EV/PV $30,000/$25,000 = 1.2 A is the answer.